Envirocon Selected to Present at the 2013 HydroVision International Conference

Envirocon was selected to participate in the HydroVision International Conference that was held in Denver, Colorado on July 23-26.  This conference is the leading annual hydro power focused event in the nation with an average of 3,000 attendees. Mr. Kris Cook a Project Manager with Envirocon was chosen to present on the Milltown Dam Remediation Project. The presentation covered the extensive project scope including the construction of a 4,000 foot long bypass channel; the diversion of the Clark Fork into a bypass channel; demolition & removal of the Milltown Dam and spillway structures; and the construction of the final channel alignment and re-routing of the river. The Milltown Project is one of Envirocon’s largest project to date, running from 2003 until 2012, with a total revenue of $75 million.