Skip to content

Dam Removal & Repository/Cap Construction

Dam-Removal_featured-1

Site Overview

Envirocon demolished two historic dams and restored a creek at this environmentally sensitive site. In addition, we re-routed the creek and restored the stream bank as part of the design/build project. We performed constructabilty reviews, managed public relations, obtained access agreements, and worked under the regulatory oversight of a trustee group and EPA Region 4.

Project Highlights

  • Demolished a 150-foot x 30-foot reinforced concrete dam
  • Lowered water levels behind the dam using 30-inch siphons
  • Provided technical constructability reviews for cell construction, dredging, dam removal, regulatory negotiations, and site restoration
  • Constructed a 27-acre, 400,000-cubic yard RCRA-equivalent repository for sediments contaminated with PCBs
  • Received 2012 Environmental Excellence Award from the National Demolition Association for continued leadership and innovation in “green” development and corporate environmental stewardship

Value Delivered

A hurricane passed over the project site during construction of the repository which resulted in a significant storm event. Envirocon’s erosion controls and mitigating actions limited the impact of the hurricane and resulted in little to no impact to the construction schedule.

4.5k
ft2 Reinforced Concrete Dam Demolished
400k
yd3 RCRA-Equivalent Repository Constructed